| Finally, the effects of resource changes are indicated in this figure. Overtime and additional personnel have negligible effect on schedules for this project at this point in its history. Making more computer time available has substantial effect. This indicates that this project is essentially though not completely limited by computer time available. If the manager can make both more computer time available and back off on the failure intensity objective, it may be possible to change the estimated completion date even further. Note that we cannot generalize to other projects. Effects of resources changes are specific to a particular project and time. |
|